ARCHIVED - Decision CRTC 2001-728

This page has been archived on the Web

Information identified as archived on the Web is for reference, research or recordkeeping purposes. Archived Decisions, Notices and Orders (DNOs) remain in effect except to the extent they are amended or reversed by the Commission, a court, or the government. The text of archived information has not been altered or updated after the date of archiving. Changes to DNOs are published as “dashes” to the original DNO number. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats by contacting us.

Decision CRTC 2001-728

Ottawa, 28 November 2001

Mr. Don B. Wohlberg
President
Askivision Systems Inc.
Box 26049
Saskatoon, Saskatchewan
S7K 8C1

Dear Sir:

Re: Application 2001-1262-3 - Approval
12-month extension of time limit
Askivision Systems Inc. - Grand Coulee, Saskatchewan

We are pleased to inform you that the Commission approves your request for an extension of time limit to implement the cable distribution undertaking to serve Grand Coulee.

The Commission grants a 12-month extension of time limit, namely until 25 November 2002, which it considers a reasonable delay to complete construction of the project.

This extension does not, of course, relieve you of your responsibility to implement the authority to operate the cable distribution undertaking at the earliest possible date.

Should the completion of new installations not be completed within the period stipulated in this letter or, should the Commission refuse to approve an extension requested by the licensee, the licence will not be issued.

As stipulated in the approval decision, the authority will only be effective and the licence will only be issued at such time as the construction of the undertaking is completed and it is prepared to commence operation.

Consequently, the applicant is required to advise the Commission, in writing, once it has completed construction and is prepared to commence operation of the undertaking, at which time, the Commission will issue the licence.

The Commission requires you to append this decision to the original decision granting you a licence.

Sincerely,

Ursula Menke
Secretary General

Date Modified: 2001-11-28

Date modified: